€15.5M data center transformation across six global sites
A six-site legacy estate consolidated and migrated with executive governance, delivering €900K in realized savings.
€900K in realized savings
6,200+ workloads migrated and consolidated
4.7–4.9/5 customer satisfaction sustained
Challenge
A multi-site legacy estate with 6,200+ workloads and 1,437+ applications, high run costs and limited visibility across a multi-vendor landscape.
Approach
- Ran discovery, application dependency mapping and disposition analysis (6R) across all six sites.
- Built the business case, wave plan and executive governance model with the client leadership team.
- Directed consolidation, hybrid migration and automation with multi-vendor delivery teams.
What I took away
- Disposition decisions hold only when the business case is owned jointly by IT and finance.
- A single executive governance forum removes far more delay than additional delivery capacity.
- Wave planning around application dependencies — not around sites — protects business continuity.
More transformation stories
BFSI
AI-enabled real-time analytics for trading and risk
Read case studyHealthcare & Insurance
Multi-region AI-ready data lake for claims and underwriting
Read case studyCloud Practice · ASEAN
Scaling a cloud practice from 41 to 167 FTEs in 90 days
Read case studyFacing a similar challenge? Happy to walk through how this program was structured and what would apply to your context.
Start a conversation